How to Effectively Manage Construction Materials

Contractors at construction site looking at material being hoisted by crane

Managing construction material is a critical part of ensuring the project’s success, given that contractors spend 40-70% of the project cost into buying building material. Yet, it is not uncommon to see large amounts of waste material at construction sites after the project is completed. With proper materials requirement planning, this would be preventable.

Material management is a complex process that can make or break a construction company. Effective material management helps get work completed on time, boosts profits, and ensures positive cash flow.

The aim of material management is to get the right quantity of construction and building materials from the right supplier, at the right time, right place, for the right cost.

1. Get the Right Quantity

construction materials of brick and cement

To get the right quantity of building materials, it is essential to have a material take-off. The purpose of material take-off is to obtain an actual total quantity of materials with the correct specification that will be used in the construction project.

Once the take-off quantity is established, it will serve as a baseline to allow the person in charge to cross examine whether materials ordered by the project site are within the project’s budget. In order to prevent multiple or over-ordering from occurring, having a system that will alert the person in charge early will be useful.

2. Choose from the Right Supplier

construction materials being transported out of factory

The cost of construction and building materials should not be the sole deciding factor for choosing the right supplier. The right suppliers should have the capability to deliver the quantity of materials you require, and to do so according to the delivery schedule. Other factors to look out for when selecting a materials supplier include credit facility and after-sales support.

It is advisable to always have at least one backup supplier for every material you order for your project site. This ensures the projects will run smoothly even if your first-choice supplier was unable to deliver for some reason.

3. Purchase at the Right Time

construction material delivered to a site that has a surplus of material

While buying your construction materials in bulk no doubt saves money, delivering these materials before they are needed may pose a few risks such as damage and theft. Furthermore, delivering large quantities of materials in advance is unwise as you will have to bear the cost of transfer and storage. Similarly, delivering the materials too late will cost you idling and operation costs.

It is always optimum to ensure construction materials are delivered right before you need to use it. This will allow sufficient time for material inspection and reduce the risk of theft and damage.

4. Deliver to the Right Place

construction material delivered to a busy construction site

Most project sites are huge; moreover, contractors may have different teams working at different locations in a project site. Loading and unloading bulky material are expensive as both will incur machinery cost.

Therefore, it is important to ensure materials are being delivered to the right place. This will eliminate double handling or unnecessary storage, and ensure the quality of material is preserved, which would otherwise be jeopardised during unnecessary double handling.

5. Purchase at the Right Cost

using a tablet to compare construction material quotations from suppliers

As contractors spend most of their project value purchasing building material, it is essential to purchase them at the right cost to ensure profitability. During the material procurement stage, it is advisable to cross check with prices quoted during the tendering stage. Price comparison and negotiation skills are useful and important in obtaining the best price possible.

In summary, it is obvious how complex the material management process can be. With so many factors at play, there are bound to be mistakes here and there, which will affect the bottom line should it get out of hand.

With evolving construction software technology these days, it can be much easier to manage, especially if your company uses an e-procurement software, or a material management module in an ERP system. One such example is Speedbrick COMPOSE, a software (mobile/desktop) that streamlines your purchasing workflow. Users of Speedbrick COMPOSE have reported positive results such as increased project profits and better materials management (purchasing costs stay within the allotted budget).

Furthermore, Speedbrick COMPOSE provides several features such as historical price trends, automatic monthly material report generation, overbudget alerts, among many others. Users can prevent duplicate efforts and have increased visibility throughout the purchasing cycle, from material request to matching.

About Speedbrick Solutions

Speedbrick Solutions builds easy to use software for contractors to do more with less. Allowing contractors to monitor risks ahead of time, on mobile. Currently Speedbrick has 4 products: procurement management, revenue management, subcontractors management and business analytics dashboard.

Currently, Speedbrick is servicing contractors in Malaysia and Singapore.

Find out more at www.speedbrick.com.

See Speedbrick in action

Schedule a free demo with us to see how we have served projects worth more than RM13.2b, and achieved 99% client satisfaction along the way.

How to Standardise Your Construction Purchasing Cycle

purchasing cycle icons over a background of a construction professional's office

The purchasing cycle in construction, from ordering materials to payment, is not easy. A well-managed procurement is often considered a major contributing factor of a successful project. Construction professionals have to source high quality materials and engage services within a specific budget, while also complying with regulations at the same time. Therefore, ensuring accuracy, timeliness and quality throughout the procurement is essential for the success of the project.

Thus, to ensure the purchasing cycle is managed effectively and smoothly, standardising and systemising the cycle should be a priority.

Doing so would decrease overall cost as there will be a decrease in waste. Furthermore, with a more standardised approach, communication among stakeholders will improve, which will decrease the risk throughout the purchasing cycle, particularly risks that have the potential of delaying project delivery and driving up costs.

The following are identifiable stages you can use to standardise your construction business purchasing cycle:

1. Quantity Take Off

Material Takeoff Icon

Identify the budgeted quantity of all raw and prefabricated materials required for the project.


2. Material/Equipment List Approval Submission

Material List Icon

Submit material specification details and authority certificates to client or superintending officer to obtain approval on material to be used in the construction project.


3. Material Requisition

Material Request Icon

Site raises material requisition (MR) according to site condition and work programme.


4. Material Approval

Material Request Approval Icon

Depending on the size of contractors, this could be a multi-tier approval. Each MR should be approved by a superior before procurement.


5. Quotation Comparison

Quotation Comparison Icon

Purchasing department obtains pricing comparison on material order. Purchasers will compare the terms and pricing between multiple suppliers, and negotiate with suppliers when necessary.


6. Supplier Selection

Supplier Selection Icon

Based on the quotations, the company will select a suitable supplier for the material.


7. Purchase Order (PO)

Purchase Order Icon

At this stage in the purchasing cycle, the order is placed and this becomes a contract between the organisation and the supplier.


8. Material Delivery

Material Delivery Icon

Supplier will deliver ordered material. During this stage, contractors will need to check that the materials are delivered according to specifications, and validate the delivery order (DO).


9. PO/DO/Invoice Matching

PO/DO/Invoice Matching Icon

When suppliers provide invoice for payment, the contractor will have to ensure invoice is according to materials detailed in PO and DO.


10. Approval and Payment

Payment Icon

Payment can only be made after the finance department has verified the invoices. Payment will be made according to the agreed credit terms.


11. Record Update

Records and Reports Icon

The material purchasing records will be updated. There are 3 types of data in a purchasing report that is important for management:

  1. Material expenses report

  2. Material quantity report

  3. Whether ordered quantity is within or exceeded budget.


As mentioned before, the purchasing cycle is complex, but it plays a crucial part in the project’s success. With the number of stakeholders involved, managing them means going through a lot of MR, PO, DO and invoicing documents—all of which may involve manually recording these documents into spreadsheets reports.

It’s time-consuming and rarely sustainable in bigger budget and complex construction projects.

It is essential to have visibility and accountability on material spending, and at every step of the purchasing cycle.

This is so that mistakes or potential errors can be identified and addressed by the stakeholders, who otherwise would run the risk of making spending decisions without knowing how their decisions affect the project’s bottom line.

The best way to ensure your purchasing cycle is standardised is to use a digital procurement platform, such as Speedbrick COMPOSE. It allows all stakeholders to perform construction material purchasing tasks on one platform.

Some of its helpful features are:

  • Available historical price trends

  • Automatic monthly material report generation

  • Seamless accounting software integration

  • Overbudget alerts

With Speedbrick COMPOSE, your procurement process will be enhanced as the software

  • Provides real-time actionable insights

  • Increases visibility and accountability across the board, managing stakeholders efficiently

  • Allows convenient and efficient procurement, also eliminating duplicate efforts

See Speedbrick in action

Schedule a free demo with us to see how we have served projects worth more than RM13.2b, and achieved 99% client satisfaction along the way.

Progress Claim Process In Malaysia

illustration of progress claim documents and parties involved with the backdrop of a construction site

Conducting payment in the construction industry is a lot different than in others. Firstly, there must be a construction contract between the contractor and its client. Then payment is made progressively, in order to aid the contractor’s cash flow, otherwise paying in full after the work is completed will lead to financial difficulties for the contractor.

Progressive payment refers to paying the contractor according to the work completed, either on a monthly basis or between the agreed duration. Therefore, in order to receive payment from the client, the contractor has to initiate the progress claim process.

There are several stipulations or requirements involved in this claims process. Both parties will have to agree to a set date for the contractor to submit their progress claim, which usually falls on the 25th of the month. Suppose the contractor fails to submit their progress claim by the date stipulated, then they will run into the risk that the claim will not be processed until the following month.

There are several contracts in which the progress claim is used, such as when the contract is entered between:

  • An employer/client and a main contractor

  • A main contractor and a nominated subcontractor (NSC)

  • A main contractor and subcontractor (domestic)

Each of these contracts have its own process that must be handled carefully.

Contract 1: Between an employer and a main contractor

  1. Generally, the contractor will prepare his progress claim and submit it to the architect. It’s also a common practice for the employer to receive a copy.

  2. The architect will then verify the work completed during the particular month and issue an interim certificate to the employer, along with a copy to the contractor.

  3. The contractor then submits their tax invoice, attached with the interim certificate (for accounting purpose), to the employer for the amount stipulated on the interim certificate.

  4. Upon receiving the contractor’s invoice, the employer will make the payment.

Progress claim process diagram in Malaysia, between employer and main contractor

Contract 2: Between a main contractor and a nominated subcontractor (NSC)

  1. The NSC will prepare his progress claim and submit it to the main contractor.

  2. The main contractor will compile the NSC’s claim and submit it as part of the main contractor’s claim to the architect.

  3. The architect will verify the work completed by the NSC during the particular month and issue an interim certificate to the employer with a copy to the main contractor.

  4. The interim certificate is then forwarded to the NSC.

  5. The NSC submits their tax invoice, attached with the interim certificate (for accounting purposes), to the main contractor for the amount stipulated on the interim certificate.

  6. Upon receiving the NSC’s invoice, the main contractor will then make payment to the NSC.

Progress claim process diagram in Malaysia, between main contractor and nominated subcontractor (NSC)

Compared to the contract between the employer and main contractor, the nominated subcontractor will be the one to initiate the progress claim, and the main contractor will issue the payment. The NSC does not directly claim from the employer.

Compared to the domestic subcontractor, the nominated subcontractor (NSC) enjoys certain privileges. They are selected by the client to carry out some of the works. Moreover, the NSC also gets their progress claim certified by the architect, which is not practiced for the domestic subcontractor.

Contract 3: Between a main contractor and a subcontractor

  1. The subcontractor will prepare his progress claim and submit it to the main contractor.

  2. The main contractor will certify the subcontractor’s completed work, usually in accordance to the interim certificate the main contractor has received from the architect.

  3. The main contractor will then send the interim certificate to the subcontractor.

  4. The subcontractor submits their tax invoice, attached with the interim certificate (for accounting purposes), to the main contractor for the amount stipulated on the interim certificate.

  5. Upon receiving the subcontractor’s invoice, the main contractor will then make the payment to the subcontractor.

Progress claim process diagram in Malaysia, between main contractor and domestic subcontractor (DSC)

In summary, there are subtleties among these contracts that must be monitored carefully.

The entire progress claim, interim certificate issuance and payment process will affect the cash flow in a construction company, and thus should be tracked properly.

Nevertheless, when a construction company handles a lot of projects, the team overseeing may overlook or delay the progress claim submission, which will impact the certification process. Other times, it can take the architect a long time to issue an interim certificate, which will subsequently delay the processes that follow.

Generally, there are many points of failure or delay in the progress claim process, which makes it even more important to monitor progress claims closely. This also highlights the need for a centralised payment platform, such as Speedbrick ECHO, where your team can obtain clean and simplified visualisations of the progress claims, which provides a clearer overview to all stakeholders.

Speedbrick ECHO enables you to track each project’s financial health at a glance, monitor claimed and certified progress to identify outstanding payments, and automatically generate project cash inflow reports.

There are many benefits to Speedbrick ECHO, as using this platform allows you to:

  • Recognise payment risks early

  • Drill down to the details of the payment

  • Identify and manage potential cost overrun scenarios before they happen

  • Reduce unnecessary effort and time spent processing financial information for reports

Here’s what our client said about Speedbrick ECHO:

It is so easy, I use Speedbrick to monitor all my projects’ payments. The system highlights outstanding payment for my immediate action. Now, I only need to focus on chasing outstanding payment. I no longer spend time compiling spreadsheet reports.
– Vivan, credit controller of Strong Force (M) Sdn Bhd

On the other hand, to manage your subcontractors and your payment to them, Speedbrick offers the Speedbrick ECHO+.

With Speedbrick ECHO+, you can do the following (and more!):

  • Supervise and track awarded, certified, and paid subcontractors on one platform

  • Maintain a directory of subcontractors

  • Create and issue standardised subcon certificate summaries

  • Approve, certify and pay subcon variation orders (VOs) in a central platform

  • Generate and link backcharges to subcon certificates

With these features, Speedbrick ECHO+ enables you to make better decisions based on real-time insights of subcontractor performance, as well as to manage your subcons easily on a single platform.

See Speedbrick in action

Schedule a free demo with us to see how we have served projects worth more than RM13.2b, and achieved 99% client satisfaction along the way.

Progress Claim Template in Excel

progress claim template with construction backdrop

Download a free Progress Claim template in Microsoft Excel format. This template consists of a workdone summary page and format of a typical construction project’s bill of quantity. 

Speedbrick ECHO offers a centralised payment platform, which enables you to monitor claimed and certified progress to identify outstanding payments, track each project’s financial health at a glance, and automatically generate project cash inflow reports. Furthermore, clean and simplified visualisations of the progress claims provides a clearer overview to all stakeholders.

There are many benefits to Speedbrick ECHO, as using this platform allows you to:

  • Recognise payment risks early
  • Drill down to the details of the payment
  • Identify and manage potential cost overrun scenarios before they happen
  • Reduce unnecessary effort and time spent processing financial information for reports

See Speedbrick in action

Schedule a free demo with us to see how we have served projects worth more than RM13.2b, and achieved 99% client satisfaction along the way.

Here’s a quick guide on how you should manage your building material inventory post MCO

construction worker inspecting steel bars

KNOW YOUR PROJECT TAKING OFF QUANTITY

Make sure you have your budget quantity estimated. Project management starts with knowing how much material you need to buy. You will not be able to control your inventory without knowing the quantity needed for your construction project. 

 

TRACK YOUR MATERIAL QUANTITY

Ensure that your site request is within your take-off quantity. Overbuying and double ordering tend to happen a lot in a construction project. When construction sites resume work after COVID-19 lockdown, it is expected that contract renegotiations will happen. Contractors’ paper-thin profit margin will be slash even further. Proper material control will help prevent leakages from happening.  

 

MATERIAL CONTROL IS EVERYONE’S JOB

The blame game tends to happen when no one takes responsibility for monitoring project material. When overbuying happens, site tends to blame the office, and the office tends to blame the site. Supply chain management is complex and it involves many departments, many stakeholders. It is hard to keep track as many companies rely on paper to keep a record. Consider switching to inventory management software that can warn you before you waste money on overbuying material. 

 

Speedbrick Solutions is a construction software company that specialises in helping its clients stay in control and ahead of construction risks. Two proven solutions are available now, Speedbrick COMPOSE: managing supply chain management risk and Speedbrick ECHO: managing project financial performance and important contractual terms, including EOT management.

Construction Sites And Covid 19, How Is The Construction Industry Affected

workers wearing mask on construction site

As the war against Covid 19 intensifies in Malaysia, the government of Malaysia has issued a restriction of movement that has essentially halted the operations of various businesses in Malaysia in order to limit the spread of the virus. On 16.3.2020, the Prime Minister, via a special message, issued the Restriction of Movement Order pursuant to Prevention and Control of Infectious Diseases Act 1988 and the Police Act 1967. The Government. 

One of his directives are as follow:

“Complete restriction of movement and assembly nationwide, including religious activities, sports, social and cultural events. To enforce this restriction, all houses of worship and business premises are to be closed, except supermarkets, public markets, sundry shops and convenience stores selling essential goods…”

However, it is unclear if the construction site falls under the definition of Business Premises. As a construction site is technically not a business premise, does this mean contractors are allowed to resume operations as normal despite this restriction? This sudden and drastic Restriction of Movement has created a lot of confusion in the construction industry as it is unclear if construction site works are allowed to operate normally. 

As a result we have a situation where some contractors continue operations and end up being fined.

The ambiguity of the order has led to different interpretations, exposing the contractors that do continue to operate during this period to the risk of jail time and an extensive fine. 

On 17.3.2020, DBKL issued a notice “Notis Pematuhan Perintah Kawalan Pengerakan” which request for construction parties including the main contractor, nominated subcontractor, domestic subcontractor, site workers, to obey the Restriction of Movement Order. It further recommends the following steps to be taken:

  1. Ensure and control the safety and cleanliness of the construction site
  2. Ensure construction sites are free from the threat of damage and theft
  3. Ensure that the proper safety record and documentation on site
  4. Have an updated photographic snapshot of the construction progress as of 17.3.2020 and to take all necessary steps to ensure that work can continue after the order has been rescinded.

Similar notices were issued by other local authorities including Majlis Perbandaran Petaling Jaya and Majlis Perbandaran Kajang, Ministry of Energy and Natural Resource 

On the morning of 18.3.2020, a Prevention and Control of Infectious Diseases (Measures within The Infected Local Areas) Regulations 2020 was gazetted, with this Regulation, it provides a glimpse of clarity that where Regulation 3 states that: 

(1) No person shall make any journey from one place to another place within any infected local area except for the following purposes:

(a) to perform any official duty;

(b) to make a journey to and from any premises referred to in regulation 5;

(c) to purchase, supply or deliver food or daily necessities;

(d) to seek healthcare or medical services; or

(e) any other special purposes as may be permitted by the Director-General.

Around evening time of 18.8.2020, the Ministry of Work released it’s Frequently Asked Questions (FAQs) answering some queries in relation to the construction industry. Briefly, it confirms that all construction projects have to be stopped apart from those that involve work that’s critical. It defines critical works as

 “kerja-kerja yang mana jika sekiranya tidak diteruskan boleh mendatangkan mara bahaya atau kemudaratan kepada pekerja, orang awam atau persekitaran”

 It gave a list of critical works as follow: 

  1. Slope Repairs;
  2. Pothole Repairs;
  3. Traffic Management Control;
  4. Examination of Lifts/Escalators/TravelatorsPemeriksaan and other critical electrical and mechanical equipment;
  5. Facility upgrading works in premises with critical services;
  6. Traffic light repairs;
  7. Construction repairs on the damaged Bailey Bridge;
  8. Emergency works that are stated on a prior contract; and 
  9. Any other construction that needs to be completed that may be a hazard. 

However, before such critical work can be carried out, recommendations letter must be obtained from the person in charge of the project / Resident Engineer / Principal Submitting Person for the project, and such recommendations need to be submitted to the relevant ministry of work / local authority for its approval. 

It looks like, apart from the exception stated in Regulation 3(1) above, no person should leave their premises at all. Together with the above FAQs issued by the Ministry of Works, it’s mostly settled that construction sites do not fall under essential services and construction sites should stop work unless it falls under the category of critical works. 

This then brings up a series of unaddressed issues/concerns such as:

  1. Does the Restrictive of Movement constitute as a Force Majeure event?
  2. Who is going to bear for the loss of time and cost?
  3. Are the contractors entitled to claim for Extension of Time (EOT)?
  4. If so, do developers get to claim for the same, and from who?
  5. What happens to the workers that are currently working? 

The Ministry of Work had made it clear that the Government will not bear for any loss and expense during this unforeseen period, it looks like many in the industry are left hanging not knowing what to do. 

On the same day, Master Builders Association Malaysia have also issued a letter to the Chief Executive of Construction Industry Development Board Malaysia (CIDB), requesting for construction work to be continued as the severity of impact toward the construction industry. In view of the FAQs issued by the Ministry of Works, the chances for the Government to resume work in the construction industry is low. 

So, what options do the industry players have? 

Malaysian Institute of Architects (“PAM”) issued an Advisory Note to its members on 18.3.2020 in which they perceive this Restrictive Movement Order does constitute as a Force Majeure event under the PAM Contract 2006 which entitles contractors to apply for EOT. 

On 19.3.2020, PAM issued another Advisory Note to its member, reminding fellow architects of their legal duty to instruct a contractor to revise the Works Programme to cater for the temporary suspension and it is at the affected contractor’s liberty to submit his claims for an Extension of Time and/or for any loss and additional expense arising. The Architects role is to ensure that these claims are submitted wholly in accordance with the terms of the contract and assessed fairly. 

With all the above information, Speedbrick would like to recommend the following steps to be taken by the contractors: 

Firstly, immediately review your construction contracts, familiarise yourself with the clauses in relation to Extension of Time and Force Majeure.

Secondly, draft the following letters to your client:

  1. To inform your client that your work is being suspended pursuant to the Restrictive Movement Order;
  2. To apply for an Extension of Time and/or any loss and additional expense arising;
  3. To notify your client of your intention to invoke the Force Majeure Clause. 

By doing so, you have fulfilled the notice requirement that may be required under the construction contract. 

Thirdly, you are to keep proper records of your current work progress and record on how you are being affected during this difficult period. Although this may not prevent the foreseeable risk and issues that are going to happen in the near future, but at least there is a proper paper trail and documentation detailing the necessary impact. 

As you may well know, the lack of clarity has brought up a bucket load of issues that will continue to compound over time, as the construction industry as a whole comes to terms with the measures taken to stop the spread of the virus. We can only hope that the chain of consequences will be minimised to prevent further unnecessary losses from continuing as a result of this order as it may heavily impact the cash flow and the financial stability of many construction companies in the industry. 

As part of the construction industry, Speedbrick recognises the difficulties that construction companies are going through. We hope that during this unprecedented time, you maintain proper documentation and site security safety to prevent any unnecessary losses on your end further. Most importantly, ensure that safety continues to be a priority for everyone involved.

Speedbrick Solutions is a construction software company specialises in helping its clients stay in control and ahead of construction risks. Two modules are available now, Speedbrick COMPOSE: managing supply chain management risk and Speedbrick ECHO: managing project financial performance and important contractual terms,including EOT management.